UPGRADE AND EXPANSION OF WASTEWATER TREATMENT PLANT (WWTP) OF LIVADIA

Published : May 10th, 2022

The JV “THALIS E.S S.A – GOLIOPOULOS S.A” on May 9,2022 signed a contract for execution of the project “ Upgrade and expansion of Wastewater Treatment Plant (WWTP) of Livadia.

The scope of the project includes:

  • The execution of the final study, the implementation study and any additional studies and research
  • Construction of civil engineering projects
  • Supply and installation of electrical and mechanical equipment
  • commissioning and completion tests
  • the test operation of the project for a period of six (6) months.
  • normal operation for a period of eighteen (18) months,
  • the mandatory maintenance for operation period